Netherlands
Energy-transition infrastructure, the MIRT pipeline, and screening under the Vifo Act.
Summary of investment context
The Netherlands traditionally finances national infrastructure through public expenditure, with private capital playing a more targeted role than in some comparable jurisdictions. Its framework combines regulatory oversight of energy network revenues, a well-regarded suite of tax incentives for sustainable investment, an extensive public-private partnership model in transport, and a long-term strategic planning architecture that provides meaningful pipeline visibility for private investors. We set out below the key features of the Dutch market, explaining how the various support mechanisms contribute to favourable risk allocation and predictable investment returns, and explore recent and upcoming changes and the impact these are likely to have on investment in the infrastructure sector.
Key Government policies and regulation attracting private capital
Economic Regulation
Public budgets play a dominant role in financing national infrastructure in the Netherlands. The Mobility Fund (Mobiliteitsfonds) has a 2026 budget of approximately €10.5 billion for infrastructure projects across the country, and economic regulation designed primarily to attract private capital is accordingly less prevalent than in some other European jurisdictions.
Where economic regulation does exist, it serves principally to calculate acceptable revenues in essential sectors like gas and electricity. The Authority for Consumers and Markets (Autoriteit Consument & Markt, the "ACM") regulates energy network prices and profits through certain of its decisions incorporating an allowed rate of return for the private provider, using models such as the Regulated Asset Base ("RAB") and weighted average cost of capital ("WACC") to determine acceptable returns.
The Netherlands has not adopted the RAB model for broader infrastructure investments, though it has been considered for certain projects — including the proposed construction of new nuclear reactors. Instead, the principal mechanism for providing revenue certainty in the energy sector is the Stimulation of Sustainable Energy Production and Climate Transition (Stimulering Duurzame Energieproductie en Klimaattransitie, "SDE++") scheme, which currently functions as an operating subsidy compensating producers for the difference between the production cost of sustainable energy and the market revenue generated. For new large-scale solar and wind projects, the current SDE++ design no longer complies with EU rules and will be replaced in 2027 by a dedicated contract for difference ("CfD") scheme, under which the Dutch State will enter into agreements based on an agreed strike price and settle the difference between the strike price and the market price accordingly.
Effectiveness: The ACM's regulatory framework provides revenue visibility for energy network investors, reducing market price and volume risk and supporting stable, utility-style cash flows. The SDE++, and the forthcoming CfD regime, provides a level of price certainty shielding investors from wholesale energy price volatility, enabling more accurate financial modelling and supporting access to lower-cost debt financing.
Challenges: The SDE++ is funded from general government budgets rather than through a levy on consumer bills, making funding availability subject to political decision-making and annual budget cycles. Applications are open only during specific windows, with the next upcoming window in September 2026, limiting the ability of investors to plan around the scheme on a continuous basis. The forthcoming transition to a CfD regime introduces near-term uncertainty about the precise terms of the replacement framework.
Revenue Support and Tax Incentives
Revenue support
Beyond the SDE++ scheme described above, certain Dutch infrastructure projects benefit from targeted market and revenue support regimes, particularly in the context of the energy transition.
Tax incentives
The Netherlands provides several targeted tax incentives aimed at encouraging investment in energy efficiency, environmental sustainability and technological innovation. These operate within the corporate and personal income tax frameworks and are available to entrepreneurs and Dutch corporate taxpayers investing in qualifying assets. The Energy Investment Allowance (Energie-investeringsaftrek, "EIA") provides an additional tax deduction of 40% of the investment amount in qualifying energy-efficient assets listed on the annually updated Energy List (Energielijst). For 2026, the budget is €460 million, with deductions capped at a maximum investment of €153 million per taxpayer.
The Environmental Investment Allowance (milieu-investeringsaftrek, "MIA") provides an additional tax deduction for investments in environmentally beneficial assets listed on the Environmental List (Milieulijst), with applicable percentages of up to 45% depending on the asset category. The 2026 budget is €135 million, capped at a maximum investment of €25 million per taxpayer. Where the EIA has been applied, the MIA cannot be applied simultaneously to the same investment.
The Accelerated Depreciation on Environmental Investments (Willekeurige afschrijving milieu-investeringen, "VAMIL") permits accelerated depreciation of up to 75% of qualifying investment costs, enhancing cash flows in the initial years of the investment with the remaining 25% following the standard depreciation schedule. The 2026 VAMIL budget is €20 million. It is possible for an investment to qualify for tax incentives under both the VAMIL and MIA at the same time.
Effectiveness: A 2023 policy evaluation covering 2017–2021 found that the MIA/VAMIL stimulated approximately €11 billion in environmental investments against a total budgetary cost of €666 million. A separate evaluation of the EIA over the same period concluded that it is a cost-effective instrument for reducing greenhouse gas emissions. The current government has committed to exploring the consolidation of the EIA, MIA and VAMIL into a single, streamlined regime.
Challenges: Free-rider rates remain a concern across the green investment schemes — estimated at between 26% and 59% for the MIA1 and between 31% and 74% for the EIA, 2 indicating that a significant share of qualifying investments would have proceeded without the incentive. All three schemes rely on annually updated qualifying asset lists, which can create uncertainty for long-term investment planning, and are subject to statutory sunset provisions (horizonbepalingen) currently set to expire on 1 January 2029 unless renewed following a mandatory evaluation.
Government Investment
The Netherlands generally relies on direct public expenditure to fund infrastructure, and co-investment with private capital is not common. The most significant infrastructure spending flows through Rijkswaterstaat, the Department of Waterways and Public Works, which utilises the Mobility Fund to invest in roads, waterways and railways.
Effectiveness: The Dutch model of direct public funding has delivered reliable and high-quality infrastructure over many decades, providing a stable and long-term funding horizon that is difficult to replicate through private capital alone.
Challenges: The heavy reliance on public expenditure means that infrastructure competes directly with other demands on the national budget, creating vulnerability to fiscal and political cycles and leaving gaps in the funding of non-prioritised assets. The Netherlands Court of Audit (Algemene Rekenkamer) has estimated a funding deficit of €20.5 billion for Dutch infrastructure through 2037, and questions have been raised in parliament about how to make infrastructure projects more attractive for private developers.
Policy and Operational Regulation
The principal instrument through which the Dutch government communicates its national infrastructure strategy is the Multi-Year Programme for Infrastructure, Space and Transport (Meerjarenprogramma Infrastructuur, Ruimte en Transport, "MIRT"), which reflects the government's long-term investment priorities and provides an overview of how planned infrastructure projects are organised and coordinated across levels of government.
Several recent initiatives have sought to improve the coordination and efficiency of consenting processes. For large-scale energy projects, the Project Procedure for National Energy Projects (Projectprocedure Rijksenergieprojecten) centralises decision-making for projects of national significance (including offshore wind farms, high-voltage transmission lines and hydrogen networks) under central government coordination. The Environment Planning Act (Omgevingswet), which came into effect on 1 January 2024, replaced and integrated dozens of existing laws relating to spatial planning, environmental protection and construction, with the objective of simplifying permitting by reducing procedural timelines and improving coordination between governmental bodies.
The Dutch government is also collaborating with grid operators, local authorities and market participants through the National Grid Congestion Action Programme (Landelijk Actieprogramma Netcongestie) to address grid congestion, one of the most material near-term constraints on private investment in the Dutch energy and related sectors. A number of potential measures to assist parties awaiting urgent grid connection have been identified, and regulatory reform in this area is anticipated, though the extent and pace of implementation remains to be confirmed.
Effectiveness: The centralised Project Procedure for energy projects and the Environment Planning Act represent meaningful steps towards streamlining the consenting environment for major infrastructure projects, reducing timeline risk and improving capital deployment velocity for private investors.
Challenges: The practical impact of the Environment Planning Act on permitting timelines will depend on implementation and on the capacity of relevant authorities to process applications efficiently under the new framework. Grid congestion remains a significant near-term constraint.
Public-Private Partnerships
Public-private partnerships ("PPPs") are used extensively for large infrastructure projects in the Netherlands, most commonly through Design, Build, Finance and Maintain ("DBFM") contracts. Under a DBFM structure, a private company or consortium delivers a defined infrastructure output over a period of 20 to 25 years, raising its own financing to fund the construction phase. The government makes no payments until the asset is available for use, with remuneration thereafter tied to meeting pre-determined performance standards rather than to demand or usage.
Effectiveness: DBFM contracts provide predictable, availability-based remuneration for private investors over long contract periods, aligning performance incentives and delivering reliable outcomes — particularly for transport infrastructure. The structure supports competitive debt pricing and gives investors confidence in long-term returns.
Challenges: As in other jurisdictions, DBFM contracts have faced criticism for the complexity and cost of procurement, limited accessibility for smaller contractors, and the rigidity of long-term contractual arrangements in accommodating changes in policy or technology over the contract term.
Infrastructure pipeline
The Netherlands does not maintain a single, centralised investor-facing project database, and pipeline visibility must be constructed from a combination of national strategic frameworks, sector-specific plans and procurement channels. The landscape offers meaningful high-level visibility through long-term strategic planning, but requires investors to engage with multiple tiers of government to identify specific opportunities.
The MIRT is the principal national strategic planning document, providing an overview of the government's major infrastructure projects through the publicly available MIRT Overview (MIRT Overzicht), which details the status, planning and background of key projects as part of the annual budget of the Ministry of Infrastructure and Water Management. The MIRT Overview is not exhaustive: it does not include purely regional or local projects funded solely by local or regional government, routine maintenance projects, or privately initiated and funded projects.
Sector-specific transparency is generally strong in priority areas. The energy transition — encompassing offshore wind, hydrogen and grid expansion — benefits from dedicated, well-publicised programmes with clear long-term goals: the National Energy Structure Programme (Programma Energiehoofdstructuur) maps out planning for major energy infrastructure, while TenneT and Gasunie publish multi-year investment plans. Road and water management projects are managed by Rijkswaterstaat, which outsources billions of euros of projects annually; a dedicated Delta Programme sets out the long-term investment strategy for flood protection and water management.
Projects procured through DBFM and other PPP structures follow regulated and transparent tender processes, with mandatory publication on TenderNed, the central digital procurement platform for all Dutch government tenders above applicable thresholds, providing a clear entry point for private capital. The Netherlands also benefits from EU-level pipeline transparency mechanisms, notably the European Commission's infrastructure project lists under the Trans-European Transport Network ("TEN-T") and Trans-European Networks for Energy ("TEN-E") frameworks.
Pipeline transparency deteriorates outside centrally coordinated sectors. The Netherlands' decentralised political structure under which provinces, municipalities and water boards have significant autonomy in initiating and developing projects, means that no single comprehensive pipeline overview exists and this approach is not expected to be materially changed in the near future. Investors must engage at national, regional and local levels to obtain a complete picture of available opportunities, and political shifts, in areas related to environmental and other policy, can create further uncertainty around specific initiatives.
Risk allocation and predictability of returns
The support mechanisms described above improve risk allocation and return predictability in distinct ways:
DBFM contracts: The Dutch DBFM model allocates construction, financing, maintenance and performance risk to the private company or consortium. Remuneration is tied to meeting pre-determined performance standards over contract periods of 20 to 25 years — rather than to demand or usage risk — delivering a stable and predictable revenue stream that supports competitive debt pricing and gives investors confidence in long-term returns.
SDE++ and forthcoming CfD mechanism: The SDE++ mitigates market price risk by guaranteeing a base amount per unit of energy produced or CO₂ avoided, shielding investors from wholesale energy price volatility. The forthcoming CfD regime will provide comparable price certainty through a strike price mechanism. Both approaches enable more accurate financial modelling, support access to lower-cost debt and provide clearer visibility on equity returns.
MIA, VAMIL and EIA: These tax incentives improve post-tax equity returns by reducing taxable income through additional deductions and accelerated depreciation, lowering the effective cost of qualifying investments and improving overall project economics without altering the underlying risk profile.
Direct public funding: While the Mobility Fund and Rijkswaterstaat primarily finance publicly delivered infrastructure, the long-term funding horizons and strategic commitment they represent provide indirect comfort to private investors participating through procurement or co-investment opportunities. The stability of multi-year commitments reduces the risk of project cancellations and funding shortfalls, supporting confidence for contractors and financiers engaged in publicly procured works.
Recent legal and regulatory change
Retroactive or quasi-retroactive change
Dutch Foreign Direct Investment Act (Vifo Act)
As a general principle of Dutch law, legislation may only have retrospective effect in exceptional circumstances. One such exception is the Dutch Foreign Direct Investment Act (Wet veiligheidstoets investeringen, fusies en overnames, the "Vifo Act"), enacted in 2023 with the aim of mitigating risks to national security arising from acquisitions in certain critical sectors, including critical infrastructure. Although the Vifo Act came into force on 1 June 2023, the regulatory framework has a starting reference date of 8 September 2020 — meaning that investments closed after that date can be reviewed retroactively by the Dutch Investment Screening Bureau (Bureau Toetsing Investeringen, "BTI") where there is reason to do so in the interest of national security.
The Vifo Act is part of a broader trend towards strategic independence. As in a number of other jurisdictions, the Dutch government has become more cautious about acquisitions of critical infrastructure by certain categories of foreign investor, resulting in an expanded list of investment screening requirements across sectors including heat transmission, nuclear energy, air transport and port operations. For investors who completed acquisitions in critical infrastructure sectors between 8 September 2020 and 1 June 2023 — on the basis of a regulatory framework that included no mandatory screening — the Vifo Act has altered the legal conditions governing those completed investments.
Tax incentive scheme suspensions
The EIA, MIA and VAMIL schemes have on occasion been suspended mid-year where the annual budget was exhausted — notably between 26 September and 31 December 2002, again at the end of 2006, and again at the end of 2007 — leaving investors who had made qualifying investments later in the year unable to claim the relevant incentives. Since 2009, the government has sought to reduce this risk through multi-year budget management, carrying forward any unutilised budget to subsequent years.
In addition, the qualifying asset lists governing eligibility for the MIA, VAMIL and EIA can under certain circumstances be amended with retroactive effect to 1 January of the calendar year in which the change is made. In a case before the District Court of Gelderland on 29 August 2025, the court ruled that the regulatory framework applicable at the time the investment obligation was entered into was decisive, and that the taxpayer could not reasonably have been expected to anticipate a later retroactive amendment to the list.
(ii) Changes made during periods when the framework was widely expected to remain stable
The nitrogen crisis
One of the most significant examples of regulatory disruption to infrastructure investment in the Netherlands is the so-called nitrogen crisis, which followed the Council of State's 2019 ruling on the Programme for Nitrogen Management (Programma Aanpak Stikstof, "PAS"). Introduced in 2015 with the aim of reducing nitrogen emissions while simultaneously facilitating economic development, the PAS was declared incompatible with EU law in 2019 — bringing many construction projects, including major infrastructure projects, to an abrupt halt. While not legally retroactive, the ruling took effect while projects were already in progress, fundamentally altering the regulatory environment on which significant capital commitments had been made. This constitutes a clear example of the "soft retrospective risk" to which long-duration infrastructure investment is particularly exposed.
Energy transition policy adjustments
Private purchase subsidies for electric vehicles were abruptly terminated on 1 January 2024 due to budget constraints, fiscal benefits related to electric vehicles have been scaled back, and the subsidy budget for renewable electricity production has been significantly reduced in response to strain on the national budget. These adjustments — made while the broader policy framework was widely expected to remain stable — illustrate the vulnerability of investor planning assumptions to in-period policy change, and reinforce the importance of robust contractual protections and change-in-law provisions in infrastructure project agreements.
Summary of regulatory environment
Investors in Dutch infrastructure face a targeted but expanding regulatory landscape. The FDI framework, combining sector-specific laws with a broader national security screening act, currently scrutinises investments in large-scale energy, telecoms, and offshore wind, although its scope remains narrower than many comparable regimes and interventions are relatively rare. In merger control, the Authority for Consumers and Markets (ACM) heavily monitors energy and digital assets. It is seeking call-in powers for below-threshold deals but uniquely champions sustainability, permitting green benefits to offset competitive concerns in specific cases. As an integrated multi-sector regulator, the ACM also oversees regulated markets (including the energy and telecoms sectors), which are undergoing significant legislative transformation.
How burdensome is the FDI regime in this jurisdiction, and are there any notable trends relating specifically to infrastructure investment?
The Dutch FDI screening framework comprises a set of sector-specific regimes rather than a single statute. Mandatory screening currently applies across telecommunications, energy and in the offshore wind sector under dedicated sectoral laws. The National Security Investment Act, in force since June 2023, operates alongside these sector laws and extends screening to a broader range of vital processes, sensitive technologies, and operators of business campuses not already captured by sector-specific legislation. All regimes are administered by the Bureau Toetsing Investeringen (BTI), and notably, the regime is jurisdiction-agnostic meaning there are no exemptions for Dutch or EU investors.
The control test and notification triggers differ across regimes. Under the National Security Investment Act, the test turns on whether an investor acquires control or significant influence over a company active in a vital process or sensitive technology area. In contrast, the telecommunications regime focuses on acquisitions of at least 30% of voting rights, while offshore wind screening applies to investors participating in permit tenders and changes of control over permit holders for wind farms not yet in operation.
Substantively, the Dutch regime is narrower than many comparable regimes. For instance, in the energy sector its scope is primarily limited to LNG facilities and large-scale electricity generation assets. Consequently, interventions are relatively rare. In 2024, the BTI conducted 83 investigations, of which 61 were under the National Security Investment Act, seven under the Offshore Wind Energy Act, and one each under the Electricity Act and the Telecommunications Act. Of the completed cases, 48 received unconditional clearance, three were approved subject to conditions, and only one transaction was prohibited.
Looking forward, the clear trend is toward expansion of the regime's scope. The Dutch government is designating additional critical infrastructure as vital suppliers — which is expected to increase the number of notifications. Furthermore, an overhaul of energy legislation effective from 1 January 2026, mandates screening role for changes of control over LNG systems and electricity producers with a nominal capacity of at least 100 MW.
What is the latest public policy direction for merger control in this jurisdiction, particularly regarding any trends relevant for infrastructure investment?
The ACM oversees Dutch merger control and has identified energy and digital infrastructure as top priorities in its 2026 Agenda. The prevailing trend is towards greater scrutiny of strategic assets, particularly in relation to private equity-driven consolidation and below-threshold transactions. To bolster oversight, a June 2025 legislative proposal seeks to grant the ACM a formal call-in power to review below-threshold acquisitions across all sectors.3
In addition, the ACM continues to champion the integration of sustainability into merger control. In its submission on the revised EU Merger Guidelines, the ACM advocates recognising out-of-market sustainability efficiencies and sustainability-focused remedies, including monitoring mechanisms. For infrastructure projects with a strong sustainability rationale, this offers a potential defensive avenue for transactions that might otherwise raise prima facie competition concerns, although the ACM stresses that such benefits must be merger-specific and cannot simply be achieved through cooperation agreements.
Recent enforcement actions highlight the ACM’s nuanced approach to infrastructure investments:
Vertical integration scrutiny: In KPN’s acquisition of Open Tower Company (passive antenna infrastructure), the ACM cleared the deal in the notification phase, but only subject to behavioural remedies. These included non-discriminatory access to antenna sites and an information protocol to prevent the exchange of competitively sensitive information. This illustrates that vertical integration – where an acquirer is also a downstream customer – can trigger close scrutiny of foreclosure risks and information advantages, even at relatively moderate market shares (30–40%).
Sustainability-driven counterfactuals: The review of the KWS/Schagen/NTP asphalt plant joint venture demonstrated a permissive approach to green capex. The ACM widened the relevant geographic delivery radius and factored in the ongoing transition to more sustainable asphalt production. Because existing plants lacked the capacity and permits for the required green investments, rendering them without a “long-term perspective”, the ACM discounted their competitive significance. This signals that the ACM may take a more permissive view of consolidation where significant capital expenditure is needed to meet environmental standards.
What is the record of sector-specific regulators overseeing infrastructure sectors in this jurisdiction and are there any key or upcoming developments to highlight?
In the Netherlands, the ACM acts as the primary regulator, holding a reputation as an independent, evidence-based, and increasingly interventionist regulator. Unlike many of its peers, the ACM integrates its role as the national competition regulator with sector-specific regulation for energy, telecommunications, and transport. It regularly publishes forward-looking agendas and policy papers, such as the ACM’s 2026 Agenda and State of the Market report, which provide investors with a roadmap of regulatory priorities. 4 Decisions made by the ACM, such as the imposition of tariffs, are subject to judicial review within the Dutch administrative court system.
The regulatory landscape in the Netherlands is currently undergoing significant legislative transformation – for instance:
District heating: The Collective Heat Act (Wcw), targeted for January 2027, will move district heating toward a more regulated, utility-style framework. Under the Wcw, heat supply undertakings will have to be predominantly publicly owned, although municipalities may utilise 20-to-30-year Public-Private Partnerships (PPPs) if public options are unviable for a specific heat parcel. The Wcw will also replace gas-linked tariff setting with a cost-based model, with the ACM supervising tariff formulas and maximum tariffs for each heat parcel.
Hydrogen economy: The National Hydrogen Programme provides a roadmap for developing the Netherlands’ hydrogen economy, achieving 3-4 GW of electrolysis capacity by 2030. The roadmap outlines policy support, infrastructure needs, and sustainability criteria for hydrogen production and use. It also includes provisions for subsidies, legal frameworks for hydrogen networks, and market incentives. In 2024, the Dutch Consumer and Markets Authority published guidelines related to third party access rights to hydrogen terminals, shaping the upstream and downstream infrastructure landscape, including ammonia cracking facilities.
Energy planning and overhaul: The comprehensive 2026 Energy Act aims to align Dutch law with EU directives, facilitate the integration of renewable energy, ensure security of supply, and enable the development of new energy carriers like hydrogen. It is aimed at facilitating the energy transition and will streamline permitting processes for energy infrastructure.5 Concurrently, the 2024 Environmental and Planning Act consolidates and simplifies spatial planning, building, environmental protection, and nature conservation. While designed to accelerate permitting for complex infrastructure developments through a more integrated framework, it faces significant practical hurdles. For example, projects involving nitrogen deposition near protected Natura 2000 sites continue to encounter severe delays, as the new system has not yet fully resolved the legal complexities in existing Dutch policy.
- Mandatory?
- Yes
- Voluntary?
- No
- Review period(s)
- Once filing confirmed complete: 8 week initial period, extendable by six months (subject to stop the clocks if information notices issued).
- Number of notifications
- 83
- Non-notified deals called-in
- N/A
- In-depth investigations
- 10
- Remedies cases
- 3
- Blocked cases
- 1
- Abandoned cases
- N/A
Endnotes
Witteveen+Bos & CE Delft. (2023). Beleidsevaluatie MIA\Vamil, Periode 2017-2021, Eindrapportage. Report. 4 April 2023, p. 46. https://www.eerstekamer.nl/overig/20230914/evaluatie_mia_vamil_2017_2021/document↩︎
SEO economisch onderzoek & CE Delft. (2023). Evaluatie Energie-Investeringsaftrek, Periode 2017-2021, Eindrapportage. Report. 14 July 2023, p. 45. https://www.seo.nl/wp-content/uploads/2023/07/2023-28-Evaluatie-energie-investeringsaftrek.pdf↩︎
See here regarding below threshold review, here regarding the ACM actively seeking call-in power and here regarding the ACM actively seeking call-in power.↩︎
See e.g. ACM Agenda 2026, State of the Market report (this has not been published in previous years), ACM Year Plan 2026 (all only available in Dutch), and specific reports for the its 2026 focus areas, including Energy (in Dutch), Digital Economy (in English).↩︎
Certain transactions may require both Vifo Act national-security screening (see the response to question 1) and an ACM permit-transfer approval under the Energy Act, while the Vifo process can be paused for information requests and extended by three months where the EU FDI screening regulation applies.↩︎
Time period subject to stop the clock. In practice, a Phase 1 decision is issued within approx. 6 weeks following the notification (including stop-the-clock), provided there are no substantial competition issues. A Phase 2 decision is in practice issued approx. 20 weeks following the request for a licence (including stop-the-clock).↩︎
See 2024 ACM Annual Report, p. 39.↩︎